MUX Timesheet Availability does not match Classic (Days)

book

Article ID: 224720

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise STARTER PACK-CLARITY PPM

Issue/Introduction

Timesheet in MUX does not match Classic view when the effort is configured in Days.  When changing the effort to Hours, they match. 


STEPS TO REPRODUCE: 

1. Select Resource and update availability to 9.5 hrs
2. Go to the Resource's calendar
3. Update the Resource's calendar to Mon/Wed shift of 9.5 hrs, Tues/Thurs shift at 4hrs and Friday Non-Workday
4. Create a new Project and add the resource on the Team
5. Create a Task and assign the resource to the Task
6. Go to Timesheets in Classic View
7. Search for the resource with timesheet status Open and click on timesheet icon
8. Click Configure on timesheet
9. Under Time Entry Options, set Display Unit to Days
10. Save and Return
11. Add the new task
      Mon/Wed - enter 1.1
      Tues/Thurs - enter .65
      Friday is blank
      Save
12. Go to Classic, Administration, General Settings, System Options 
      Under 'New User Experience' check 'Activate Timesheets, Save 
      Log out then log back in 
13. Go to MUX 
      Verify that effort is in Days under Settings 
      Click on Timesheets 
      Search for the resource 
      Go to the timesheet 


Expected Results: The timesheet should match what was entered in the Classic view. 

Actual Results: The timesheet is showing more than what was entered.  When changed Effort to Hours, it matches Classic view.  Database is correct as well. 

Workaround: None. 

Environment

Release : 15.9.1, 15.9.2

Component : CLARITY TIME MANAGEMENT

Resolution

This is DE60880, resolved in 15.9.3

Fix: Instead of Resource calendar, Modern UX will be taking the Standard calendar which is similar to Classic.