Timesheet availability in the Modern User Experience (MUX) does not match the Classic view when the effort is configured in Days. When changing the effort to Hours, they match.
STEPS TO REPRODUCE:
- Select a resource and update the availability to 9.5 hrs
- Go to the resource's calendar
- Update the resource's calendar as the below:
- Mon/Wed shift = 9.5 hrs
- Tues/Thurs shift = 4hrs
- Friday = Non-Workday
- Create a new project and add the resource to the team
- Create a task and assign the resource to the task
- Go to Timesheets in Classic View
- Search for the resource with the timesheet status of Open and click on the timesheet icon
- Click Configure on the timesheet
- Under Time Entry Options, set Display Unit to Days
- Save and Return
- Add the new task
- Mon/Wed - enter 1.1
- Tues/Thurs - enter .65
- Friday = blank
- Save
- Go to Classic, Administration, General Settings, System Options
- Under 'New User Experience' check 'Activate Timesheets and Save changes
- Log out then log back in
- Go to the MUX
- Verify that effort is in Days under Settings
- Click on Timesheets
- Search for the resource
- Go to the timesheet
Expected Results: The timesheet should match what was entered in the Classic view.
Actual Results: The timesheet is showing more than what was entered. When changed Effort to Hours, it matches Classic view. The database is correct as well.