In Classic Clarity, ETC Cost and Allocation Cost display only zero values in the Projects although the 'Update Earned Value and Cost Totals' job has been run. Also from the Project - Task list page, the 'Update Cost Totals' Action has been run but it's not picking the rates from the nbi_proj_res_rates_and_costs' table. 'nbi_proj_res_rates_and_costs' table is correctly populated resource rates.
This has been reported as DE62472 and has to do with the specific setup of the rate matrix dates as they relate to the project/team/assignments.
On both allocation and assignment, if there is only 1 segment the cost is 0. If there are more than 1 segments the costs calculate correctly. We also observed that if you have more than one segment but the values are the same, for instance on allocations the % allocation = 50% on all the segment rows the costs still show as 0. When we change the default allocation with more than one segment already showing the segments do not shrink back to 1, they stay broken out but all show the same allocation %. This also makes the cost revert to 0. The only way to have the costs (allocation and ETC) is to have more than one segment.
Steps to Reproduce:
Expected results: a cost is displayed
Actual Results: 0.00 for cost
Expected Results: a cost is displayed
Actual Results: you get a cost
Expected Results: a cost is displayed
Actual Results: 0.00 for cost again
It appears that if the rate matrix doesn’t have that ‘future’ row, the cost will always be calculated correctly.
Release : 15.9.3 specific
Component : CLARITY FINANCIAL MANAGEMENT