Trying to include a task that is a subproject, in the main project status report using the option "Include in Status reporting" but get this error message:
PRJ-07243: Action cannot be performed against subproject or proxy tasks.
Is it possible to include a task(subproject) in the status report with the option "Include in Status Reporting"?
Any Clarity release
The entire 'proxy task' record is read-only - we are not allowed to edit anything on that 'task' because it is not a real task, but a pointer to the sub-project.
This is currently working as designed.
A workaround is creating a new task and adding this subproject task as a child of it. That new task can be included in the status report.