Allocations not populated correctly through xog

book

Article ID: 223705

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

When a Resource Allocation is Xogged into a project, even after running the Time Slice job the Allocation total populated on the 'Team - Staff' / 'Team - Detail' remain 
incorrect till the Resource - 'Staff Member Properties' page is open and the 'Save And Return' button and clicked (which forces insta slices to refresh).


STEPS TO REPRODUCE: 

1. Using the attached xog file, xog the resource onto a Project
2. Open the Project - Team - Detail page, the TSV values would be blank 
3. Run the Time Slice job and refresh the page to see populated data in the TSV page 


Expected Results: Allocation total should display correct value. 

Actual Results: Allocation total value is not correct until 'Save And Return' button is clicked on in 'Staff Member Properties' page. 

Environment

Release : 15.9.1, 15.9.2, 15.9.3

Component : CLARITY XML OPEN GATEWAY (XOG)

Resolution

Based on the Xog file provided it was determined that the behaviour is not a defect with the following reasons;

In the XOG file, the finish timestamps are all 1 second after midnight on the last day of the month.  

In general the finish dates are set to midnight on the day following the last day to include.  

If you want allocation to include May 31 the finish timestamp should be "2021-06-01T00:00:00" instead of "2021-05-31T00:00:01".