What is the default sort order for the Timeline in the Portfolio Items menu

Environment

Release : SAAS

Component : Timeline

Resolution

The sort order is by Planned Start Date within each project.  Beyond that, data is sorted by Object ID which generally follows the Formatted ID in chronological order.

If two items don't follow that sort order, it would be recommended to inspect the planned start date to see if was off by some small amount of time as compared to other work items.