Task Timeline Gantt bars do not end in the right place when Quarters are selected in MUX

book

Article ID: 222860

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

Gantt bars are not being placed correctly when Quarters are selected as periods in the Modern User Experience (UX)

Steps to reproduce are as below:

  1. Navigate to the Modern UX -> Projects -> Tasks Timeline
  2. Create Tasks with the following Start and End Dates:
    • Task 1:
      Start Date = 1-Aug-2021
      End Date = 31-Dec-2021
    • Task 2:
      Start Date = 1-Oct-2021
      End Date = 31-Dec-2021
  3. Click on "View Options". Select Periods = Months. Notice where the Gantt bars end
  4. Click on "View Options". Select Periods = Quarters. Notice where the Gantt bars end

Expected Result:
Gantt bars end at the end of Month = Dec 2021, and Quarter = Q4 2021

Actual Result:
Gantt bars end at the end of the Month = Dec 2021. However, they do not end at the edge of Quarter = Q4 2021

Cause

This is due to a defect with ID DE62373.

Environment

Version: 15.9.3

Resolution

Fix to this defect is available in the following version(s):

  • 16.0.0
  • 15.9.3.1

Additional Information

See also: Tasks / Assignments - Master KB for known issues