Show Tasks in filter in report Resource Forecasted Utilization Detail doesn't work

book

Article ID: 222192

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

The Resource Forecasted Utilization Detail report contains the Show task boolean input parameter selection

Selecting does have an affect. It continues to display the tasks in the report whether it is selected or not

 

Steps to Reproduce

1. Select the Forecasted Utilization Detail Report either through Reports and Jobs or Advance Reporting

2. Enter values for in required input parameter

3. Scroll down to the Show Tasks option and toggle it off.

4. Run the report

 

Expected Results: The tasks do not appear in the report

Actual Results: The tasks still display in the report.

 

Environment

Release : 15.9.2, 15.9.3

Component : CLARITY JASPERSOFT

Resolution

DE62261 is being researched by engineering.