Clarity PPM: In MUX, under Custom Investments or Projects, Staff tab weekly time scale is not reflecting any Start or End Period in the view.

book

Article ID: 221840

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

Under MUX, the weekly Timescale view does not have a Start and End Period under the Staff tab for Custom Investments and Projects

Cause

The Weekly Timescale  values are dependent on the Fiscal periods. If there are no weekly fiscal periods under the Entity, the Weekly Timescale will not have a Start and End Period. 

Resolution

Create the weekly fiscal periods in the Entity and activate them. 

Run the below jobs sequentially after creating the Weekly periods. 

Datamart Extraction

Datamart Rollup

Time Slicing