Some Jobstreams that run once per day are using Average Duration for Late Time Criterion instead of Average End Time.
search cancel

Some Jobstreams that run once per day are using Average Duration for Late Time Criterion instead of Average End Time.

book

Article ID: 221157

calendar_today

Updated On:

Products

Automic Automation Intelligence

Issue/Introduction

Some Jobstreams that run once per day are using Average Duration for Late Time Criterion instead of Average End Time.

Environment

Release : 6.3.0

Component : AUTOMIC AUTOMATION INTELLIGENCE INTEGRATION FOR BMC

Resolution

Jobstreams that run once per day should be using Average End time for the Late Criterion is based on field on the Late Criterion tab of a Jobstream.

Jobstreams that run multiple times per day should be using Average Duration.

Defect DE510996 has been resolved in 6.4.3.