Some Jobstreams that run once per day are using Average Duration for Late Time Criterion instead of Average End Time.
Release : 6.3.0
Component : AUTOMIC AUTOMATION INTELLIGENCE INTEGRATION FOR BMC
Jobstreams that run once per day should be using Average End time for the Late Criterion is based on field on the Late Criterion tab of a Jobstream.
Jobstreams that run multiple times per day should be using Average Duration.