Scheduling requirements:
Jobname Leader runs every 5 minutes between 5 AM and 10:40 AM.
If job returns CC=00, then trigger 2 other jobs, and bypass 2 jobs that normally run at 10:41 AM.
If job returns CC=04, no additional job triggering is needed. The 2 jobs that are scheduled at 10:41 AM should be allowed to run.
Release : All Releases
Component : ESP Workload Automation
JOB Leader
RUN ANY
RELEASE ADD (Jobn1.rc00) COND(RC(00))
RELEASE ADD (Jobm1.rc04) COND(RC(04))
ENDJOB
JOB Jobn1.rc00
RUN ANY
IF %ESPSHH EQ '10' AND %ESPSMN GE '40' AND %ESPSMN LE '45' THEN +
ESPNOMSG AJ Mjobs BYPASS APPL(%ESPAPPL..%ESPAPGEN)
RELEASE ADD(Jobn2.rc00)
ENDJOB
JOB Jobn2.rc00
RUN ANY
ENDJOB
SUBAPPL Mjobs
JOB Jobm1.rc04
IF %ESPSHH EQ '10' AND %ESPSMN GE '40' AND %ESPSMN LE '45' THEN +
RUN TODAY
EARLYSUB 10:41
RELEASE ADD(Jobm2.rc04)
ENDJOB
JOB Jobm2.rc04
IF %ESPSHH EQ '10' AND %ESPSMN GE '40' AND %ESPSMN LE '45' THEN +
RUN TODAY
ENDJOB