The global access rights, “Project - Task Management – All” is not working

book

Article ID: 221047

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS Clarity PPM SaaS

Issue/Introduction

  • Access rights Name: Project - Task Management – All
  • Access rights Description: Allows users to create, view, update, delete tasks and assignments for which the user has access to view projects.

In Classic View

The users who have Project - Task Management - All rights are expected to be able to Create/Edit/Delete Tasks in projects even if they are not the Project Manager

Cause

Working as Designed

Environment

Release : 15.8+

Component : CLARITY USERS, GROUPS, OBS ADMINISTRATION

Resolution

Project - Edit Management access right needs to be included to be able to Create/Edit/Delete Tasks

Additional Information

Project - Task Management – All

This access right only applies to the Modern UX, it does not change anything in the Classic view