Resolution:
In the Weekly Allocation option section the field 'Threshold Aggregation Function' is set to [--Select--], and not to Maximum.
Steps to update Studio configuration:
- Login as an administrator user
- Navigate to Administration, Studio: Objects, Team Object
- Go to the Team Object, Views tab (if you are using partitions, be sure to update view for each partition as needed)
- Click [Options] link for the 'Resource Allocations - Detail' view (Category = List Column)
- In the 'Column and Bar Graph Summary' section, click on the column link 'Allocation By Period'
- In the 'Primary Column' section, set the 'Threshold Aggregation Function' = Maximum
- Click 'Save and Return', then 'Save and Return' again
- Because the 'Options' are updated, you have to 'Publish' the changes for all users to see the change