Project Task Timelines not displaying after deleting tasks with actuals
book
Article ID: 220276
calendar_today
Updated On: 11-03-2023
Products
Clarity PPM SaaS
Clarity PPM On Premise
Issue/Introduction
Project Task Timelines are not showing after deleting tasks that has posted actuals, timesheet transactions processed by the Post Timesheets job.
STEPS TO REPRODUCE:
- Post Actuals to a project task with the Post Timesheets job.
- Open the Modern UX > Task > Timeline view
- Delete a Task that has Actuals posted to it.
Expected Results:
Timeline is shown
Actual Results:
No Timeline view is displayed.
The Board and Grid view results display.

Instead it shows:

Environment
Release : 15.9.2
Component : CLARITY PROJECT MANAGEMENT
Resolution
This is resolved in 15.9.3, reported as DE62008