Issue/Introduction

Description:

We are receiving an error message when attempting to submit a Cost Plan as a new Budget Plan.

Steps to Reproduce:

  1. Home, Projects, Financial Plans: Cost Plans, Create a Monthly cost plan
  2. Mark it as a 'Plan of Record'
  3. Click 'Submit Plan for Budget Approval' Action Link
  4. Fill in all required fields, click 'Submit for Approval' button

Expected Result: A new budget plan is created and ready for review
Actual Result: Red Error message appears - 'REVMGR-20931: Invalid period(s)'  

  

Solution:

This error occurs if a period mismatch exists (i.e. if an annual budget exists, then the current submitted POR must be of annual periods also).

In this case, an Approved Budget already exists with a structure that uses 'Annual' Fiscal Periods. When the end-user submitted the Cost Plan for approval as the new budget, the new 'Start Period' and 'End Period' values were 'Monthly' periods instead of 'Annual' periods.

When there are existing Budget plans, the 'structure' or properties of the Budget Plan are locked and cannot be changed. All new cost plans being submitted for approval as a new Budget Plan must have the same structure which includes the 'Group By', 'Sub-Group By', and Fiscal Period type (Annual, Monthly, etc.)

To resolve this issue, create a new Cost Plan (POR) with the same structure as the Budget Plan of Record (POR), and then submit it for approval.

NOTE: After clicking the 'Submit Plan of Record for Approval' Action Menu Link, if the page does not have the required attributes displayed, this error could appear when clicking the 'Submit for Approval' button.  If the 'Submit for Approval' page is blank, or it is missing the required attributes, the submission cannot process the request without the Start Period and End Period values.  Go to Studio to review the Cost Plan Layout:Edit views. 