Issue/Introduction

SUMMARY: 
If a Task's Name has a greater than/lesser than symbol in it, the name is blank while in the Timeline View

STEPS TO REPRODUCE: 

1. Create a Task from the Classic UI with the name "<test>", or from the Modern UX open the Gantt View and rename a Task to "<test>".
2. Within the MUX open a Project, go to "Tasks" and change to the Timeline View.

Expected Results: 
The name should display

Actual Results:
The Task displays in the list, but the name is blank

Environment

Release : 15.9.2

Component : CA PPM SAAS PROJECT MANAGEMENT

Resolution

This problem is resolved in release 15.9.3, and is associated to Defect DE61563.

Workaround: 
If the Task is created in the MUX interface, the name gets saved as "&#60;task2&#62;", and it displays correctly in the Timeline View.
The problem happens if the characters are saved in the record. It works correctly if the record is saved with the HTML code value. The Classic Interface does not save with the code value, and neither does the Gantt view.

Additional Information

These tasks are displayed in the Grid view

The same Tasks in the Timeline View

Notice the Task named "&#60;test&#62;" displays as "<test>" in the Timeline view, while the Task name "<test>" is blank.

 