My tests are ending abruptly before reaching its end time

 

 

Environment

Release : SAAS

Component : BLAZEMETER FUNCTIONAL TESTING

Cause

Pause too high between Thread Groups.

Resolution

After reviewing the  JMeter script, you are pausing way too high on each Thread group.

On thread group bzm - Concurrency Thread Group_Commissioning you are pausing 40 minutes.

On thread group bzm - Concurrency Thread Group_Quality you are pausing 30 minutes.

On thread group bzm - Concurrency Thread Group_Survey you are pausing 30 minutes.

When the BlazeMeter backend for an extensive amount of time it considers the test and inactive and will terminate it.

I suggest to not configure pauses over 5 minutes.  After change the test ran with no issues.

Performance tests should not have a wait time between 30 to 40 minutes, if you do, it will start declaring threads inactive and terminate the test.