search cancel

Cannot change period to weeks in Modern UX Task Timeline

book

Article ID: 216819

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

We see that we cannot change the "Periods" to "Weeks" in Modern UX -> Projects -> Tasks -> Timeline. When we set it to that option and reopen the View Options pop-up, we see that the "Periods" would have reverted to "Months". A sample screenshot is shown below.

Environment

Version: 15.9.0

Resolution

This issue is no longer seen in version 15.9.2.