Modern UX show wrong Scheduler format (OWB instead of MSP)

book

Article ID: 216665

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

One of our users has different options between the classic UI and the Modern UX. When he navigates to the Task tab of a project in the classic UI, under the Open in Scheduler he had both options for MSP Read-Write and Read-Only.

But in the Modern UX, he has options for Workbench.

Environment

Release : 15.8.1

Component : CA PPM MICROSOFT PROJECT (MSP)

Cause

This issue is due to the field being secured in Modern UX, and the user not having rights to the secured field. 

Resolution

The field can be configured to not be secure, or the user can be granted "view" rights to the secure field in Modern UX.