Large String attribute on Task object not available on Status Reports
search cancel

Large String attribute on Task object not available on Status Reports

book

Article ID: 215644

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

We have enabled Tasks to be available on Status Reports.  We created a Large String attribute (With an API Attribute ID) on the Task object, however it is not available for selection on the Status Report in the Modern / New User Experience (UX).  String attributes show up correctly. Is this expected?

Environment

Release : All Supported

Component : Project Management

Resolution

Large String attributes for Risks, Issues, Changes, and Tasks on the Project Status Report are not supported. (This includes both Plain and Rich Text Large String attributes). See  Customize the Project Status where this is referenced on techdocs.

Additional Information

See Customize the Project Status (Section: Add Risks, Issues, Changes, and Tasks to the Project Status) for more details on Tasks Project Status functionality.