Negative values display as "(" instead of a negative number
book
Article ID: 215455
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
In the Modern User Experience (MUX), negative numbers are not seen / the value is not visible. When the value is negative, it sometimes displays as '(' and not the negative number. This issue happens in areas including:
Financials module such as the Cost Variance field (in Financial Plans, it displays the correct number)
Custom Sub Sub Objects views
Custom Investment cost plans
Steps to Reproduce for Cost Variance:
Create a new project Blueprint and add the Financials module to the Blueprint
In the Modern UX, create a new project (open for time entry and financially enabled)
Assign the project to the new Blueprint
Add a resource to the project team
Create a new task and assign the resource to the task
Go to the Timesheets module, and submit time for the resource for the task in step 6
Approve the Timesheet, wait 5 minutes then run the Post Timesheets job
Run the Post Transactions to Financial job then run the Post to WIP job
Go to the Financials module of the project
Create a new Cost Plan
Click on the link to the Cost Plan
Populate from Assignments
From the View Options drop down select the following:
Per-Period Metrics: Cost, Cost Variance, and Actual Cost
Periods: Months
Start Period and End Period: Leave as the defaults
In the Per Period Metrics period that actuals were submitted for, update the Cost so that it is less than the Actual Cost
View the Cost Variance amount for the period
Expected Results: Value displayed for Cost Variance is in parenthesis (500) to reflect a negative value
Actual Results: The number is not displayed, just the first part of the parenthesis “(“
Steps to reproduce for a custom sub object:
Click on a project
Click on a sub object module
Click on a sub object instance from the grid
Click the Details Flyout
Click on the Sub Sub object module
Add a number or money field to the grid view
Populate the field with a negative value
See screen shot below. On the right hand side you can see the negative value has changed to a '('
Environment
Release : 15.9.2
Component : CLARITY FINANCIAL MANAGEMENT
Cause
Caused by DE61020
Resolution
This issue is fixed in 15.9.2 patch 1 and 15.9.3
Workarounds:
For Projects
Use the Financial Plans module instead of the Financials module until this issue is resolved.
For the Sub Sub object Grid
Click the Expand button on the grid.
2. This will generate a popup window that displays the value correctly:
For Custom Investments
The one option would be to export the data to CSV where the data shows correctly:
Click on the 3 dot icon (Options) on left hand side of Cost Plan