Last Status Update in Monitoring View Summary tab shows not correct timestamp of last job run

book

Article ID: 214433

calendar_today

Updated On:

Products

CA Workload Automation AE

Issue/Introduction

In the WCC 'Monitoring' tab, when selecting a view, then in the 'Summary' tab we see the following

    - Auto Refresh is selected and it says it is updated on 2:19:53 PM (today) (this changes every x-seconds)

    - however under the 'View Name' we have 'Last Status Update" which mentions April 18,2021 10:58:17 PM (yesterday)

 

    - however when we look at jobs in this view, we see that several jobs ran on April 19

Environment

Release : 12.0

Component : WORKLOAD CONTROL CENTER

Resolution

This is working as designed.

Last Status time which is shown in "View summary" panel is the time at which the status of the view was last changed. It is updated only when the view the status is changed.

For example if a view status is 'success' and if a job is/goes to success again, it will still show the same  "Last status time" as there is no change in view status.
But, if a job within this view runs and goes to 'failure', then the view will change to 'failure' and the last update status will change accordingly.