Cost Plan 'Planned Cost' Field Being Zeroed Out
search cancel

Cost Plan 'Planned Cost' Field Being Zeroed Out

book

Article ID: 213581

calendar_today

Updated On:

Products

Clarity PPM SaaS

Issue/Introduction

A project cost plan is zeroing out the planned cost totals. 

Environment

Release : 15.9.1

Component : CA PPM SAAS FINANCIAL MANAGEMENT

Cause

This is by design.

If the View options Start Date is modified, e.g. from Jan to Feb, it will zero out the cost plan duration for the prior months.

 

This can be supported by setting the audit trail on the cost plan object attributes Start and Finish Dates.

Resolution

Repopulate using the Populate from Team or Task Assignments options or re-enter the information manually.

Attachments