The Task hierarchy does not display in the task list, but shows up in Gantt and MSP. What is the expected result?
Release : 15.8
Component : CA PPM PROJECT MANAGEMENT
By design the hierarchy of tasks will only display in Gantt, or while using another project management tool (for example Microsoft Project). The hierarchy does not display while viewing the list of tasks in Clarity.