Aggregated attributes - What is the unit of display?

book

Article ID: 212132

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

We have created an aggregated attribute in the Team object. It adds "Pending Actuals" from Assignments. When this attribute is displayed in the List view in Classic UI or the Grid view in Modern UX, the number displayed does not change with the "Unit of Measure" setting. How to interpret the numbers displayed against this attribute?

Environment

Version: 15.9.1

Resolution

1. Aggregated attributes derive their display settings from Administration -> Project Management -> Settings

2. If the "Default Display Unit for Work Effort" in that page is "Days", then Aggregated attributes display numbers in days. If that field has "Hours", then the numbers are displayed in hours

3. This behaviour is identical between the Classic UI and Modern UX.