We have created an aggregated attribute in the Team object. It adds "Pending Actuals" from Assignments. When this attribute is displayed in the List view in Classic UI or the Grid view in Modern UX, the number displayed does not change with the "Unit of Measure" setting. How to interpret the numbers displayed against this attribute?
Version: 15.9.1
1. Aggregated attributes derive their display settings from Administration -> Project Management -> Settings
2. If the "Default Display Unit for Work Effort" in that page is "Days", then Aggregated attributes display numbers in days. If that field has "Hours", then the numbers are displayed in hours