In MUX Financials module, for example Ideas->select an Idea -> Financials, the view defaults to Cost Plans. If you do not select a cost plan and instead click on Budgets or Benefit plans, you cannot navigate back to Cost Plans.
STEPS TO REPRODUCE:
Open MUX and navigate to Ideas or Investments, select a record and browse to Financials tab. Cost Plans view displays. Click on Budgets or Benefit Plans, then try to navigate back to Cost Plans
Expected Results: Cost plans are displayed
Actual Results: Nothing happens when clicking on Cost Plans
Workaround: Click on Actual Transactions, and then Cost Plans link once again becomes operational
Release : 15.9.1, 15.9.2
Component : CA PPM SAAS FINANCIAL MANAGEMENT
This is logged as defect DE60233 and is now FIXED in 15.9.3