When a user refreshes a Gantt chart and then attempts to modify a Task date for example, the date does not get changed.
STEPS TO REPRODUCE:
1. Open a project
2. Click on Tasks
3. Open Gantt view
4. Refresh Gantt view
5. change “Start Date” in a task
Expected Results: Start Date and End Date changes to the new dates and the old dates are displayed in red.
Actual Results: Start Date and End Date stays the same.
Release : 15.8.1
Component : CA PPM PROJECT MANAGEMENT
Resolved in 15.9.3
Workaround:
Try to change the date again the second time and this will get changed.