Date on Gantt not changed after refresh of Gantt page

book

Article ID: 210652

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

When a user refreshes a Gantt chart and then attempts to modify a Task date for example, the date does not get changed.

STEPS TO REPRODUCE: 

1. Open a project
2. Click on Tasks
3. Open Gantt view
4. Refresh Gantt view
5. change “Start Date” in a task

Expected Results: Start Date and End Date changes to the new dates and the old dates are displayed in red.

Actual Results: Start Date and End Date stays the same.

Environment

Release : 15.8.1

Component : CA PPM PROJECT MANAGEMENT

Resolution

Resolved in 15.9.3

Workaround:
Try to change the date again the second time and this will get changed.