I can auto-schedule a user's Project using the Gantt tool, but they cannot.  They are listed as the Project Manager of the Project and all Task changes have been saved.

The auto-schedule option is greyed out for them in the Gantt tool. What access rights are needed for the manager to autoschedule?

Environment

Release : All Supported

Component : CA PPM SAAS PROJECT MANAGEMENT

Resolution

A combination of the below would give the user the autoschedule right. 

  • Project - Edit Management:  Instance Access or 'Project - Edit Management - ALL' - Global Access
  • Project - Schedule in Browser: Global Access only

Note: The global schedule in browser right will only give the user access to autoschedule projects they have project edit management rights to.

Additional Information

See the following KB for more detail on the schedule in browser right: Project Schedule In Browser Access Right