Some actuals appear to be missing from the Project Grid, Ideas Grid or Custom Investments Grid.
You will see the same behavior on Actuals on the Project List page in Classic.
All
Please check to make sure the Investment Allocation Job is executed after posting Timesheets and Financial actual transactions.
This job updates the total investment-level usage and baseline values for the Projects.
Read more information on the purpose and overview of the job in additional Knowledge Articles
** Enhanced ** in Release 16.0.2:
Prior to 16.0.2:
Description of what the job does (Prior to 16.0.2)
What is the Investment Allocation job purpose?
Investment Allocation Job - Purpose & Overview (Broadcom KB)