When creating a new cost plan in the new UX for ideas Finish Period dates have auto populated in the past based on the project dates and after 15.9.1 upgrade finish period is not populated if project finish date falls on the last day of the month.

book

Article ID: 209312

calendar_today

Updated On:

Products

Clarity PPM SaaS

Issue/Introduction

SUMMARY: When creating a new cost plan in the new UX for ideas Finish Period dates have auto populated in the past based on the project dates and after 15.9.1 upgrade finish period is not populated if project finish date falls on the last day of the month.

STEPS TO REPRODUCE: 

1. Login to Clarity Modern UX and ensure idea is financially enabled so cost plan can be created
2. Set Finish date on the idea to any last day of the month (ex. 7/31/2021)
3. Attempt to create Cost Plan and notice Finish Period is not auto populated

Expected Results: Finish Period should auto populate based on finish date of the idea

Actual Results: Finish Period is not auto populated

Note: Same behavior could be observed for projects and CITs

Workaround: Manually populate Finish Period

 

Environment

Release : 15.9.1

Component : CA PPM SAAS FINANCIAL MANAGEMENT

Resolution

DE59893, Under review by Engineering team.