Modern UX: New Cost Plan Does Not Have Finish Period Date Populated

book

Article ID: 209312

calendar_today

Updated On:

Products

Clarity PPM SaaS

Issue/Introduction

When creating a new cost plan in the new UX for Ideas or Projects, the finish dates are not auto populated. 

This happens after the 15.9.1 upgrade.

STEPS TO REPRODUCE: 

1. Login to Clarity Modern UX and ensure idea is financially enabled so cost plan can be created
2. Set Finish date on the idea to any last day of the month (ex. 7/31/2021)
3. Attempt to create Cost Plan and notice Finish Period is not auto populated

Expected Results: Finish Period should auto populate based on finish date of the idea

Actual Results: Finish Period is not auto populated

Note: Same behavior could be observed for projects and CITs

Workaround: Manually populate Finish Period

 

Cause

This is due to the project/idea having a finish date falling on the last day of the month.

 

Environment

Release : 15.9.1

Component : CA PPM SAAS FINANCIAL MANAGEMENT

Resolution

This is reported as DE59893, under Engineering team review.