Unable to inactivate projects and update financial status simultaneously using xog in gelscript

book

Article ID: 209181

calendar_today

Updated On:

Products

Clarity PPM On Premise

Issue/Introduction

<gel:parse> is sorting the project tag properties in alphabetical order due to which the project xog is unable to inactivate the project since we are closing financial status together.

 

Environment

Release : 15.9, 15.9.1

 

Resolution

This is how the product is designed, in order to deactivate the project the financial status should be set to closed first and then only project should be deactivated, hence the xog code needs to be broken down into two parts