DE59801 Roadmap not showing in Timeline View with start/finish conditions are met, due to midnight date
search cancel

DE59801 Roadmap not showing in Timeline View with start/finish conditions are met, due to midnight date

book

Article ID: 208745

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

STEPS TO REPRODUCE:

  1. Create a new project starting 1/1/2020 with finish 12/31/2023
  2. Now go to Modern UX - Roadmaps
  3. Create a new Roadmap from 1/1/2021 - 12/31/2023 (note same day as project's finish)
  4. Add the project to the Roadmap via Import from PPM
  5. Now look at the Timeline View

 

Expected Results: The project to be displayed in the timeline, as per the rules, because the finish date is 12/31/2023 and not later than the Roadmap end (also 12/31/2023)

Actual Results: The project does not display in Timeline view, just in the other views. In inv_investments we can see the finish day is saved as 12/31/2023 17:00

Similar issue may happen with start date when it clashed with the midnight date.

Environment

Release : 15.7.1 -15.9.1

Component : CA PPM PROJECT MANAGEMENT

Resolution

DE59801, fixed in 15.9.2

Additional Information

For more information on the rules of display of roadmaps by date, see below: https://knowledge.broadcom.com/external/article?articleId=96805