Unable to modify out of the box (OOTB) scheduled instance of Time Slicing Group By job

STEPS TO REPRODUCE: 

  1. Once customer upgraded to 15.9.1 Time Slicing Group By job will be scheduled to run every 5 minutes.
  2. As an admin on the system you can't see the status of the job unless you set a debug on from Edit configuration page.

Expected Results: You should be able to see Time Slicing Group By job log

Actual Results: You can's modify the scheduled job definition, get an error
NJS-0119: At least one parameter is invalid. Check the parameters and submit again.

Environment

Release : 15.9.1

Component : CLARITY FINANCIAL MANAGEMENT

Resolution

DE59799, Fixed in 15.9.2.

Note: The name of the job has changed in 15.9.2 from 'Time Slicing Group By' to 'Time Slicing Sync' (ID=TIME_SLICING_SQLCURVE)

Workaround: Pause out of the box scheduled box and re-schedule with same Unix crontab */5 * * * *