To Do Scoreboard - Task Date with No date on the To Do displays as current date

book

Article ID: 208028

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

We go to Modern UX - Tasks - To Dos and filter by Due Date on the To Dos. We can see that the To Dos with no Due Date display as Current Date every time. How would a PM know if the date is empty and how can they filter on this?

Environment

Release : 15.8.1, 15.9, 15.9.1

Component : CA PPM PROJECT MANAGEMENT

Resolution

This is by design. Product Management are working on completely refactoring the To Do Scoreboard in this iteration. Which means that the new page should go in our next release.