STEPS TO REPRODUCE: 

1. Navigate to Modern UX 
2. Open any project with 1 task on it
3. Go to Status module 
4. Add Current Phase attribute and put it anywhere on the report 
5. Observe no values available to select 


Expected Results: status Report “Current Phase” shows parent tasks from the project task list 

Actual Results: No values are available under 'Current Phase'. If you save the attribute from Classic and open it in Modern UX it shows, but if you try to change it will show no results again.

Workaround: None. 

Environment

Release : 15.9

Component : CA PPM APPLICATION

Resolution

This is DE59617, NAB

The design of the Current Phase lookup will only display "Phases". and not tasks (nor milestones). A phase is something at topmost level and has a grouping of tasks underneath.

In summary, the field will display all tasks that have a subtask on it