The company is upgrading Clarity servers Linux OS, and migrating to new servers. Is there any sequence of steps to migrate the Clarity Application servers to the new machine?
Release : Any
Component : CA PPM APPLICATION
The steps to use on the new server would be
- Create the Clarity user on the new server
- Create the Clarity installation directory on the new server
- Install the OpenJDK from the Clarity PPM installation media
- Install Tomcat from the Clarity PPM installation media
- tar zxvf the copied file of the Clarity installation directory
- Amend the properties.xml for server name, OpenJDK and Tomcat changes.
- Redeploy the Clarity PPM services.