The field % Complete Calculation Method is not selected when a new project is created via the board, so user must perform additional steps to select the values.
STEPS TO REPRODUCE
Expected Results: The field % Complete Calculation Method to be prepopulated in the Board Create view as default is set to this required field
Actual Results: The field % Complete Calculation Method is not selected, which means that it requires the user to do the additional actions to select the values.
Release : 15.7.1 - 15.9
Component : CA PPM PROJECT MANAGEMENT
Workaround: Do not use Board - Create, or fill all the required fields manually
This is DE59612, NAB, it will be addressed by a user story instead, due to the complexity of the fix.