Task Owner field: Map to MSP

book

Article ID: 207476

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

Is there a way to map the Task Owner field's data to Microsoft Project (MS Project) so that when I download a project, the task owner information also gets downloaded along with the tasks?

Environment

Release : 15.7.1 and Higher

Component : CA PPM PROJECT MANAGEMENT

Resolution

It is possible to create a MSP Mapping (Export only) to export the Task Owner value to MSP. Below are the steps to do that:
  1. In Clarity, go to Administration->Project Management->MSP Field Mapping
  2. Click on New
  3. Enter the following:
    • Object Type: Task
    • Data Operation: Export
    • PPM Attribute ID: task_owner
    • MSP Field Name: Text10 (or select any text field outside Text1-5 that is not already in use in your system)

    4. Click Save and Return

Note: It's not possible to use Data Operation options of Import or Import and Export, as the Task Owner data is not able to be saved back from MSP. 

Additional Information

See also: Task Owner field: What is it used for?