Modern UX - After adjusting and deleting posted Timesheets in Modern UX, the Actuals in PPA_WIP tables are not removed(negated).
STEPS TO REPRODUCE:
1. Create a Project with a Task. Allocate and assign a labor resource to the Project & Task
2. Login to Modern UX Timesheet and enter actual on the project/ task created in step one above (ensure it is only one line entry in the Timesheet)
3. After five minutes run these jobs - (post timesheet, post financial transactions, post to WIP)
4. Check Actuals at assignment level (task) and Actuals in cost plan. Actuals show correctly
5. Go back to the Modern UX Timesheet which was previously posted and click on Adjust button
6. Delete the line entry in the timesheet (we have only one line) by hovering mouse on the Task name to display the three dots to the right of task name then click on it to
display the 'Delete' button. Delete the timesheet entries
7. Submit the empty timesheet and approve it
8. After five minutes run these jobs - (post timesheet, post financial transactions, post to WIP)
9. Check Actuals at assignment level (task) and Actuals in cost plan
Expected Results: Actuals to be removed from Task Assignment level and cost Plan
Actual Results: Actuals have not been removed from the Cost plan but only from Task Assignment
Release : 15.7.1, 15.8, 15.8.1
Component : CA PPM FINANCIAL MANAGEMENT
DE53149, not reproducible in 15.9.0
Workaround: Do not use 'Delete' button in the Modern UX Timesheet