DWH portlet shows Duration in red and Is Not Updating the Load End Date
search cancel

DWH portlet shows Duration in red and Is Not Updating the Load End Date

book

Article ID: 206053

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

The Data Warehouse Audit portlet shows Duration in red and Is Not Updating the Load End Date

STEPS TO REPRODUCE:
1. Run the Load DWH and wait for its completion
2. Navigate to Administration -> Security and Diagnostics -> Data Warehouse
3. Look at the "Data Warehouse Audit" portlet
4. Sort by 'Load End Date'
5. Review the 'Duration' column.

Expected Results:
They should not be any negative results as the job completed.

Actual Results:
There are negative times showing.

Environment

Release : 15.8

Component : CA PPM SAAS APPLICATION

Cause

DE59307

Resolution

This is has been reported to Sustaining Engineering to be investigated