Running autoschedule removes the assigned resource's ETC value on the project. This does not happen for all tasks and occurs both in Open Workbench (OWB) and the Clarity Gantt.
Steps to Reproduce:
Expected Results: The task start and finish date change to a new date based on the Autoschedule Date selected and the ETC is moved to that date.
Actual Results: The task start and finish date change to the expected new date, but the ETC is now 0.
Release : 15.8, 15.8.1, 15.9, 15.9.1, 15.9.2, 15.9.3
Component : CLARITY OPEN WORKBENCH (OWB)
DE59293 -
This issue occurs when the following criteria are met:
Workaround:
Fixed in Release 16.0.0