Autoschedule in OWB and Gantt moves ETC for a resource
search cancel

Autoschedule in OWB and Gantt moves ETC for a resource

book

Article ID: 206012

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

Running autoschedule removes the assigned resource's ETC value on the project. This does not happen for all tasks and occurs both in Open Workbench (OWB) and the Clarity Gantt. 

Steps to Reproduce:

  1. Go to Administration - Base Calendars
  2. Open the standard calendar and make 1/1/2021 a non-workday
  3. Create a new project with dates of 1/1/2021 to 12/31/2021
  4. Add a resource to the team with 100% allocation
  5. Create a task with dates of 1/1 to 1/1 and mark is as Fixed Duration (notice that the duration is set to 0 days)
  6. Assign the resource to the task, and add a non-zero amount of ETC
  7. Autoschedule the project in either the Clarity Gantt or in OWB with the following options: 
    Autoschedule Date: 1/5/2021 (or any other workday)
    Resource Constraints: Checked

Expected Results: The task start and finish date change to a new date based on the Autoschedule Date selected and the ETC is moved to that date. 

Actual Results: The task start and finish date change to the expected new date, but the ETC is now 0. 

Environment

Release : 15.8, 15.8.1, 15.9, 15.9.1, 15.9.2, 15.9.3

Component : CLARITY OPEN WORKBENCH (OWB)

Cause

DE59293   - 

This issue occurs when the following criteria are met:

  1. The task has the same start and finish date. AND
  2. This date is a non-workday/holiday AND
  3. The task is a fixed duration task  

Workaround:

  1. Increase the task duration OR 
  2. Leave the duration the same, but change the date to a work day OR 
  3. Set the task to NOT be a Fixed Duration task 

Resolution

Fixed in Release 16.0.0