Timesheet gauge ignores resource DOH/DOT

book

Article ID: 205696

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

The timesheet gauge ignores the resource DOH (Date of Hire) or DOT (date of Termination)

Steps to Reproduce:

1. Create a user ResA with all rights
2. At the Home > Resources side, edit the resource above
3. Set the date of Hire as 12/4/20 (December the 4th)
4. Ensure the Track Mode is set to PPM and is Open for Time entry
5. Create a project that spans from 11/1/20 till 12/31/20
6. Add ResA as team member
7. Log in as ResA to the Modern UX
8. Go to the Modern UX > Timesheets
9. Go to the Nov 30-Dec 6 timesheet

Expected Results: Timesheet gauge to display 8 Hours of availability 00.00/08.00
Actual Results: Timesheet gauge displays 40 Hours of availability 00.00/40.00

Cause

This is caused by DE59199

Resolution

This is targeted to be fixed in 15.9.2 and backported to 15.9.1.1

Additional Information

Same scenario applies to the Resource DOT (Date of Termination)