Timesheet gaudge ignores resource DOH/DOT

book

Article ID: 205696

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

The timehseet gaudge ignores the resource DOH (Date of Hire) or DOT (date of Termination)

Steps to Reproduce:

1. Create a user ResA with all rights
2. At the Home > Resources side, edit the resource above
3. Set the date of Hire as 12/4/20 (December the 4th)
4. Ensure the Track Mode is set to PPM and is Open for Time entry
5. Create a project that spans from 11/1/20 till 12/31/20
6. Add ResA as team member
7. Log in as ResA to the Modern UX
8. Go to the Modern UX > Timesheets
9. Go to the Nov 30-Dec 6 timesheet

Expected Results: Timesheet gaudge to display 8 Hours of availability 00.00/08.00
Actual Results: Timesheet gaudge displays 40 Hours of availability 00.00/40.00

Cause

This is caused by DE59199

Resolution

This is currently under Engineering review

Additional Information

Same scenario applies to the Resource DOT (Date of Termination)