When attempting to update a custom investment task finish date or ETC, the changes do not stick and the values go back to the previous values set.
There is an assignment on the task, but no actuals or ETC are on the task
Steps to Reproduce:
Log in to Modern User Experience (MUX)
Navigate to Investments
Filter for Investment
Click Tasks
Update the finish date of the task
Expected Result: Finish date is updated
Actual Result: Finish date reverts back to previous finish date.
Release : All Supported
Component : CA PPM SAAS PROJECT MANAGEMENT
If a task previously had time posted against it, and then the timesheet was adjusted where hours for the task were reduced to 0, the task is not able to be updated.
To check if this is the cause:
The one option would be to add an additional assignment to the task to make the ETC/Date editable. You can then adjust the finish date and add ETCs, and then remove the new resource from the task if needed. Dates and ETC will then still be editable.