We have a resource with Availability of 2 hours. When we try to enter 2 hours for hard allocation for the user, it automatically reverts back to 1.82.
Release : All
Component : CA PPM PROJECT MANAGEMENT
This issue can happen if the availability was updated for the resource instead of changing the resource's calendar shifts to update the availability. Updating the resource calendar automatically updates the availability.
To change resource availability, update the resource's calendar shifts instead of directly updating availability.
To fix the impacted resource's availability: