Costs and Benefits Not Showing Expected Value in Hierarchy
search cancel

Costs and Benefits Not Showing Expected Value in Hierarchy

book

Article ID: 204218

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

In an investment hierarchy, some of the cost and benefit values are not showing the expected values (sometimes even just zero).

Environment

Any Clarity release.

Cause

In order for the costs and benefits for a child investment to match the values shown when checking that child investment 'Self' value, its allocation value needs to be 100%. If the allocation % is different, costs and benefits will be calculated accordingly.

For example, if an investment with a Planned Cost of $264,400 is 0% allocated to this investment, the Planned Cost shown in the investment hierarchy will be $0:

Resolution

Change the allocation % to the desired value.

An investment may be allocated to multiple parents, with any allocation value between 0% and 100%. Regardless of how many parents have an investment, allocations total value must be either 0% or 100%.