New UX: Creating Project from Template, Dates are not retained

book

Article ID: 204033

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

Modern UI - When creating a new project from Template, the start and end dates of the project and tasks are not retained.

 STEPS TO REPRODUCE: 

  1. In classic UX, create a project template with tasks and specify start and finish dates for each
  2. In Administration, Objects, the Project Object, Attributes, set the attribute default date to a Specific Date for the Start and Finish attributes
  3. In Administration, Objects, the Project Object, Views, Project Properties, Fields, make sure ‘No Override Date’ is selected for Start Date and Finish Date in those attributes’ properties
  4. In the New UX, create a new project from the template created in step 1

Expected Results: Project and Task start and finish dates respect the template and/or object properties settings

Actual Results: the start and finish dates default to the current date in New UX. In Classic UI this works properly.

Environment

Release : 15.8

Component : CA PPM SAAS PROJECT MANAGEMENT

Resolution

A new feature has been introduced in 15.9.2 that allows the start and finish dates to be defined during the creation from the template. The ability to specify the dates during the creation is defined in the Blueprint's template settings.