Modern UI - When creating a new project from Template, the start and end dates of the project and tasks are not retained.
STEPS TO REPRODUCE:
Expected Results: Project and Task start and finish dates respect the template and/or object properties settings
Actual Results: the start and finish dates default to the current date in New UX. In Classic UI this works properly.
Release : 15.8
Component : CA PPM SAAS PROJECT MANAGEMENT
A new feature has been introduced in 15.9.2 that allows the start and finish dates to be defined during the creation from the template. The ability to specify the dates during the creation is defined in the Blueprint's template settings.