There is not an arrow showing a dependency when the dependency is from one task to another task that is off the screen
The arrow is visible when opening in Gantt
STEPS TO REPRODUCE:
PreReqs
Create a Project with tasks, enough where you have to scroll to see them all.
1. New UX - Open Project
2. Go to Tasks Module
3. Open in Gantt
4. Make a couple of dependencies on close tasks
5. Make a dependency from the first task to the last task
6. Close Gantt
7. Go to Timeline View
Expected Results: See a reference to the dependency just created
Actual Results: Do not see any reference to the dependency from the first task to the last task. Also, when scrolling, the arrows temporarily disappear
Workaround: Use Gantt instead of Timeline View
Release : 15.8.1, 15.9
Component : CA PPM SAAS PROJECT MANAGEMENT
DE58770
This is resolved in 15.9.2 with the new Timeline component introduced in that version.