Steps to Reproduce:
- In Classic UI, with auto-numbering turned on for Cost Plan
- Click Home > Projects
- Click on financially enabled project name
- Click on Financial Plans
- Select the check box in front of a Cost Plan (create one if one doesn't exist) and select Actions > Copy Cost Plan
- Click Save
- See new Cost Plan, named Copy of <previous cost plan name> and Plan ID based on auto-numbering format
- In New UI, click Projects
- Click on same project name as #3
- Click on Financials (configure this module in Blueprint if it doesn't exist)
- Right Click on the Copy of <previous cost plan name> and select Copy
- Click Create
Expected Results:
See Cost Plan ID in auto-numbering format
Actual Results:
See Cost Plan ID as Copy of <previous id>