Why is it that we see a large % number in the status column (Monitoring tab) when a jobstream is predicted as late?
397035% Late
91314% Late
Release : 6.0.1
Component : AUTOMIC AUTOMATION INTELLIGENCE ENGINE
There are a few things that can throw off late predictions.
1. If you just added the jobstream it may need some time to calculate the averages.
2. Cross instance jobs for a scheduler not yet added to AAI within a jobstream.
You will see green lines in the Gntt chart which means its tied to a Cross Instance job, they should point to a job named "cross_instance_job" which is a dummy job place holder for a job we don't have.
If we don't have the job that is linked to the target job it can cause issues with predictions.